Newsletter 9: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #9 from highways contractors at Crosskeys Roundabout Progress since 16th August  During the last two weeks we have completed the verge work outside M&S garage and between the A38 from Stroud/Whitminster, with the footway/cycleway now ready for the surface to be laid.  The central reservation between the A38 toward/from Gloucester is also well underway, […]

0 - General Updates

Newsletter 8: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #8 from highways contractors at Crosskeys Roundabout. Progress since 2nd August During the last two weeks we have installed the drainage, constructed the new widened carriageway and the shared use cycleway/footway in the verge outside M&S on the A38 towards Stroud/Whitminster. The footway/cycleway outside McDonalds has been constructed, ready for surfacing. We have also […]