Newsletter 8: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #8 from highways contractors at Crosskeys Roundabout. Progress since 2nd August During the last two weeks we have installed the drainage, constructed the new widened carriageway and the shared use cycleway/footway in the verge outside M&S on the A38 towards Stroud/Whitminster. The footway/cycleway outside McDonalds has been constructed, ready for surfacing. We have also […]

0 - General Updates

Newsletter 6: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #6 from highways contractors at Crosskeys Roundabout. Progress since 4th July During the last two weeks we have continued to work near the retaining wall along the A38 approach from the M5 (previously the B4008) to install the surface of the new widened carriageway. We have also filled the footway ready for the surface […]

0 - General Updates

Hunts Grove Drive is being extended

Posted on
Hunts Grove Drive

Big changes are coming over the next three months at Hunts Grove regarding access and construction traffic. Hunts Grove Drive is the main road around Phase 1, starting at the entrance from Marconi Drive and ending at a dead-end by Shorn Brook and the main play park. That’s all changing now with works underway to […]

0 - General Updates

Newsletter 4: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #4 from highways contractors at Crosskeys Roundabout. Progress since 7th June During the last two weeks we have installed the retaining wall and drainage along the A38 approach from the M5 (previously the B4008). We’ve completed the temporary surface on the inside lane of the roundabout and installed drains near the site of the […]

0 - General Updates

Newsletter 3: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #3 from highways contractors at Crosskeys Roundabout. A38 Cross Keys Roundabout Improvements Bulletin 3 – 7th June 2019 Progress since 24th May Drainage pipes and cable ducts have been installed within the roundabout island and kerbs have been set along the new line of the roundabout. Preparations for the new carriageway surface are underway. […]

0 - General Updates

Newsletter 2: Crosskeys Roundabout Works

Posted on
Highways Improvements

Newsletter #2 from highways contractors at Crosskeys Roundabout. A38 Cross Keys Roundabout Improvements Bulletin 2 – 24 May 2019 Progress since 13 May We set up our traffic management around the island with a new solid white line and cones around the roundabout and barriers along the approach from the M5 (previously the B4008). We […]